AFD NIROTH WATER SUPPLY PROJECT, Credit Facility Agreement 1075 03S
- Objectives: To respond to increasing demand for safe and constant water supply by extending the water production facilities, thereby contributing to improve living environment of inhabitants including the poor in Greater Phnom Penh area, and also improve the investment environment.
- Original and Revised amount: · 16,000,000.00 EURO
- Source of funding: AFD
- Effectiveness date: May 08th, 2009
- Original Closing date: June 31st, 2013
- Name and Address of PPWSA: No.45, Street 106, Sangkat Srah Chork, Khan Daun Penh
- Name of Project Director (Contact Information): H.E Ek Sonn Chan, General Director of PPWSA
- Task Team Leader's Name: Ms. Hofmann Alexia Tel: +855(0)12 201 511
- Contact information in the AFD : AFD Phnom Penh Office Tel: +855(0)23 426 360
- Procurement Status
Consultant Service
• Contract Name:+ Niroth-CS-01A PPWSA/AFD (The Consulting Services for Supervision of The Construction of Niroth Water Production Facilities (PhaseI))
• Consultant Name:SAFEGE Ingénieur Conseils
• Contract Start:May 3rd, 2010
• Contract Finish:2013
• Percentage Completion:
- The Activity 1 design review is not necessary: the same SAFEGE team performed the design.
- The activity 2 Bid evaluation and contract preparation is completed (100%).
- The activity 5 on time basis already started from 20th of April 2010.
- 31% achievement on January 31th, 2011, corresponding to Activities 2&6 and 9 months on time based. (Progress Report No 4, January 2011)
Civil Work
• Contract Name: + Niroth-CW-01A PPWSA/AFD (The Construction of Intake and RWTM)
• Contractor Name:Moya Dayen of Singapore
• Contract Start:August 5th, 2010
• Contract Finish:February 4th, 2013
• Percentage Completion:12% (Progress Report No 4, January 2011)
Goods
1.Contract Name:+ Niroth-01G-PPWSA/AFD (The Supply and Delivery of Treated Water Transmission Mains, Fittings, Valves, and Appurtenances for the Priority)
• Supplier Name:Saint Gobain PAM
• Contract Start:September 30th, 2009
• Contract Finish:September 16th, 2010
• Percentage Completion:100%
2.Contract Name:+Niroth-2G-STM1-PMU/AFD (The Supply and Delivery of DIC pipes, Fittings and Accessories)
• Supplier Name: N/A
• Contract Start:N/A
• Contract Finish:N/A
• Percentage Completion:In the Evaluation Process
• Planned and actual disbursements by sub component:Refer to Work Sheet For Quarterly For Year 2010
• Annual financial statements and audit opinion:Audit Financial Statement 2009
• Identifying contracts to be procured in next 12 months +Niroth-2G-STM2-PMU/AFD (The Supply and Delivery of STM-stage 2, Length: 2700m, DN 1200 )